Highway 1 - Nelson Creek Bridge

Construction Updates

Construction Activities

For the month of April:

  • Bearing replacement under the west end of the bridge and line marking on the road are scheduled for Monday, April 20th from 10:00 pm to 5:00 am. We anticipate one lane closure during the work. The work is weather dependent.
  • Roadside barriers removed at the west end of the structure will be restored in late April.
  • Kingston Construction's hours of operation will be Monday to Friday from 6:30 am to 3:30 pm.
  • A final update will be issued once the project is complete. Thank you for your patience!

Trail Closures

The Trans Canada Trail under the west end of the bridge has been restored. The trail is now open to the Public.

Traffic Impacts

There will be no more traffic impacts associated with this project with the exception of a lane closure at night for barrier restoration at the west end of the bridge. During that time, one westbound lane will be open to traffic and no delays are anticipated.

Please visit www.DriveBC.ca and follow us on Twitter for ongoing construction updates.

Cycling Detour

The cycling detour has been removed and cyclists are now able to freely cross the bridge in both directions. Thank you for your patience during construction.