Highway 1 — Capilano Road to Westview Drive Shoulder Widening
|

Planting (Environmental)
During the Open House August 22, 2011 there were inquiries whether residents could plant English Ivy on the sound walls, unfortunately English Ivy is considered an invasive plant.
The Ministry would like to suggest planting other species which are either native or non-invasive ornamentals.
Reference Materials
Grow Me Instead

The Invasive Plant Council of BC website
Help Stop the Spread of Invasives

Metro Vancouver
Alternate plant species suggested by the coordinator of the Greater Vancouver Invasive Plant Council:
- Western honeysuckle (Lonicera Ciliosa)
- Boston Ivy (Parthenocisus tricuspidata)
- Purple Wintercreeper Euonymus
- Taiwan Creeping Raspberry
- Coastal Strawberry
- Wild Blueberry
Project Limits
The Site is located on Highway 1 from the Capilano Road eastbound on ramp to Edgemont Boulevard o/p (approx. 1.5km), Highway 1 eastbound east end of Capilano Bridge to Bowser Ave (approx. 135m) and Highway 1 eastbound Capilano on-ramp island (approx. 15m).
Objectives
Improve safety for motorists by constructing wider shoulders that are suitable for future use and can be implemented within the constraints of the project.
Project Scope
- Widen shoulder except where structures create pinch points to a minimum of 2.5m (1.5km).
- Maintain or re-establish adjacent pedestrian path to 2m width
- Pathway to be extended 213m west and tie-in to the Pemberton pedestrian o/p.
- Entire length of pathway to have separation from traffic (880m) by concrete barrier.
- Install 900m absorptive sound wall from the Capilano on-ramp to 70m east of MacKay Ave., 3-4 meters high.
- Construct 460m concrete block retaining wall east of MacKay Ave to 190m west of the Edgemont Boulevard o/p.
- Install 570m safety railing east of MacKay Ave.
- Realign approximately 50m of pavement markings west of the Edgemont Boulevard o/p
- Utility and signage relocations
- Drainage improvements
- Not in scope – Replacing or alteration to existing structures.
- Not in scope - Widening on the north side (westbound) of Highway 1 (sufficient shoulder allowance).
Construction Description
Due to the high day time traffic volumes eastbound on Highway 1 night work should be anticipated for construction works which would impact traffic.
Construction is anticipated to begin in December and be complete by March 31, 2012 (see construction schedule).
- Survey and layout
- Construction of highway sub-grade including grubbing, stripping, excavation and embankments
- tree limbing, tree removal, removal of wire mesh fence and wooden fences and removal of existing sound wall at Lloyd Ave.
- Supplying, hauling and placing sub-base and base course aggregates, and widening with new asphalt road structure
- Pavement cutting and mill & fill
- Supply of hot-mix asphalt, hauling and paving
- Ditch construction, retaining walls, drainage
- Environmental monitoring
- Temporary and permanent pavement markings, signing
- Quality control of the work
- Traffic management and communications
- Site cleanup, revegetation and restoration
|